Azerbaijan's Zangezur Corridor main road 95% finished, state agency says PHOTO
Construction of the Horadiz–Jabrayil–Zangilan–Aghband road in Azerbaijan, part of the Zangezur Corridor, has reached 95% completion, as per the statement by the State Agency of Azerbaijan Automobile Roads.
The agency says the main road spans 123.6 km, Caliber.Az reports.
According to the agency's statement, the Zangezur Corridor project is being implemented in line with modern standards and high-quality requirements. The total length of the project is 149.9 km.
The road is designed as a 1B technical category, allowing for high-speed and safe travel. Key parameters include:
-
Road width: 14–21 metres
-
Roadbed width: 21.5–29.5 metres
-
Number of lanes: 4–6
These specifications are intended to ensure comfortable and unobstructed traffic flow along the corridor.
By Khagan Isayev